Holy Cross sanctuary was built in 1873. It was renovated in 2019. Our church purchased it in October 2020. Our first worship service was held in the sanctuary on November 1, 2020. Having been built in 1873, there were no restrooms. Knowing restrooms and space to have fellowship were needed, we are thankful that God blessed us with the funds to build a parish house. It is only through Him that this building is possible. To God be the glory!
Holy Cross Sanctuary

Groundbreaking (May 2022)


Some of our in-person and Zoom members were able to take part in the groundbreaking.
Pinning of Parish House (May 2022)




Digging and Pouring Footing (June 6-9, 2022)







Blocks, Bricks, Sand Delivered (June 10, 2022)



Building Porch and Foundation (June 14-15, 2022)









Moving Dirt Toward Foundation (July 1, 2022)




Excavation Completion (July 7, 2022)




Floor Joists and Subfloors Installed (July 28, 2022)








First Wall is Up (July 29, 2022)






One, Two, Three–LIFT! (August 1, 2022)








Putting Up Inside Studs (August 3, 2022)






And the Roof Goes Up (August 5, 2022)









Roof Covering (August 8, 2022)






And the Porch is On (August 9, 2022)



Breezeway Roof Installed (August 10, 2022)
Writing God’s Word Inside the Walls (August 14, 2022)–Ongoing































Tin Roof is On (August 29-30, 2022)




Digging the Well (September 6, 2022)


Windows Delivered and Installed (September 27-October 1, 2022)





Front and Back Doors Installed (October 12, 2022)


Electrical and Deck Framing Installed (October 31-November 2, 2022)






Wiring/Plumbing Inspection Completed and Insulation Installed (November 28-December 1, 2022)



Drywall Installed (December 10, 2022)




Mud Application on Drywall (December 12, 2022)







Trim Work and Hanging of Doors (December 27, 2022)





The Opening of Breezeway from the Sanctuary to the Parish House (January 3, 2023)



Kitchen Walls Painted and Cabinets Installed (January 12, 2023)


Outside Siding Started, Inside Painting Completed, Septic System Installed (January 16-20, 2023)



Cutting and Installation of Door from Sanctuary to Parish House (January 23-24, 2023)


Outside Siding Completed (January 24, 2023)

Fan, Lights, and Cedar Posts Installed (January 25-26, 2023)



Sidewalk Laid (February 2, 2023)


The Parish Hall Is Complete (February 18, 2023)










Dedication Service (February 19, 2023)









